On this page
  1. Aims of the Rules
  2. Four Nations Four Systems
  3. What Counts as Building Work
  4. Building Control or Installer
  5. Jobs You Need Not Report
  6. Projects Outside the Rules
  7. Part L Fuel and Power
  8. Responsibility for Breaches
  9. Certificates and Enforcement
  10. Extensions Glazing and Solar
  11. Impact on Independence

Building regulations set standards for the design and construction of buildings to ensure the safety and health of people in or around those buildings1. In England, most building work must comply with the Building Regulations 2010, which cover the construction and extension of buildings2. They also include requirements to ensure that fuel and power is conserved, which is why they matter to anyone installing a heating system, insulation, solar panels or new windows3. They are separate from planning permission: planning deals with whether a project is acceptable in principle and how it looks, while building regulations deal with how it is built.

The system works through approval, inspection and certificates. In almost all cases, work must be notified to a building control body before it starts, either a local authority team or a private registered building control approver4. Some work can instead be self-certified by an installer registered with a competent person scheme, which is instead of getting building regulations approval5. At the end, the building control body issues a completion certificate, or a final certificate if the body is a private approver6. This page explains each stage, what counts as building work, what is exempt, and what happens if the rules are ignored.

The aims of the rules

Building regulations exist to ensure the safety and health of people in or around buildings1. The Building Regulations 2010 cover the construction and extension of buildings in England, and building work must meet all relevant requirements of them2. The requirements themselves are short legal statements, and they reach well beyond structure and fire safety: they also include requirements to ensure that fuel and power is conserved3, which is the hook on which most home energy work hangs.

The practical guidance comes in the Approved Documents. These set out what, in ordinary circumstances, may be accepted as one way to comply with the Building Regulations4. That wording matters: the Approved Documents are guidance, not the law itself, and a builder can propose a different way of meeting a requirement, though most follow the documents because doing so is the straightforward route. For a household, the documents are the reference point for what an inspector will look for, from the U-value of a new wall to the ventilation that must accompany tighter insulation.

The guidance changes over time. The Building Regulations etc. (Amendment) (England) Regulations 2021 changed the guidance, including the Approved Documents, from June 20228, and the Future Homes and Buildings Standards are to be implemented via the Building Regulations etc. (Amendment) (England) Regulations 20269. A project approved under one edition is judged against that edition, which is one reason the date of an application matters.

Four nations, four systems

Four small simplified houses in a row, each in a different plain colour, each with a document sheet lying beside it showing only blank lines and plain colour bands, suggesting each UK nation has its own building rules.
Each nation sets its own building rules

The Building Regulations 2010 apply to England2, and the 2021 amendment regulations apply in relation to buildings and building work in England10. Wales shares much of the historical framework, and some regulations extend to England and Wales, but Wales now issues its own guidance: the Welsh Approved Document L, for example, is a separate consultation document with its own figures11. Electrical installation work in homes and gardens in England and Wales must comply with the building regulations12.

Scotland and Northern Ireland are different systems altogether. The UK government states plainly that there are different rules in Scotland and Northern Ireland13. In Scotland, the building regulations always apply where construction occurs, unless exempted by regulation 3, and construction includes alterations and extensions as well as entirely new buildings; the duty to comply lies with the owner, or in some cases the client, and on completion the owner or client must certify that the works have been constructed in accordance with the building warrant and the building regulations14. Northern Ireland has its own Building Regulations 2012, intended to ensure the safety, health, welfare and convenience of people in and around buildings15.

This page is about England. The same principles of approval, inspection and certification run through all four systems, but the bodies, the documents and the thresholds differ, and a household in Cardiff, Edinburgh or Belfast should read the rules for its own nation. We cover those separately in building regulations in Wales, Scottish building standards and building regulations in Northern Ireland.

Which jobs count as building work

Building work is defined in regulation 3 of the Building Regulations16. The Planning Portal lists the types of project that amount to building work, and the list is broad17:

  • The erection or extension of a building
  • The installation or extension of a service or fitting which is controlled under the regulations
  • An alteration project involving work which will temporarily or permanently affect the ongoing compliance of the building, service or fitting with the requirements relating to structure, fire, or access to and use of buildings
  • The insertion of insulation into a cavity wall
  • The underpinning of the foundations of a building
  • Work affecting the thermal elements, energy status or energy performance of a building

The regulations will probably apply if you want to put up a new building, extend or alter an existing one, or provide services and fittings in a building such as washing and sanitary facilities, hot water cylinders, foul water and rainwater drainage, replacement windows, and fuel burning appliances of any type16. They may also apply to certain changes of use of an existing building16. The Welsh list is materially the same, including the insertion of insulation into a cavity wall18.

A cutaway diagram of a house showing Regulation 3 categories of building work: a new extension at the side, cavity wall insulation being inserted, a hot water cylinder and fuel-burning appliance with flue liner as controlled services, underpinned foundations, and external wall insulation on a thermal element.
What Regulation 3 treats as building work, including work affecting thermal elements and energy performance. Image: Illustration

Two points catch households out. First, "controlled services and fittings" reaches deep into home energy work: hot water cylinders, fuel burning appliances of any type, and drainage are all named16. Second, the alteration category is not about size but about effect: work that affects ongoing compliance with the structure, fire or access requirements is building work even if it looks minor. Even relining a flue during renovation, refurbishment or repair is building work within the meaning of regulation 3 and must not be undertaken without prior notification to the local authority19.

Getting sign off: building control or a registered installer

Once work counts as building work, there are two routes to lawful compliance. The first is approval from a building control body. There are two types: a local authority building control body, and a registered building control approver4. You can apply for approval from a private registered building control approver in England if the work does not include a higher-risk building; the approver will tell the local authority about the work, called giving an "initial notice"13. In almost all cases of new building work it is necessary to notify a building control body in advance of any work starting19.

The second route is self-certification. An installer, for example of windows or boilers, who is registered with a competent person scheme can self-certify that their work complies with building standards, and this is instead of getting building regulations approval5. Notifiable work must be reported to the local building control body unless completed by someone registered on the competent person scheme20. For electrical work, the choice is stated as either arranging for the works to be inspected and tested by a person who is a member of the Competent Person Scheme, or depositing a Building Regulations Application with the Building Control Team, as full plans or a building notice21. We cover the schemes in more detail in competent person schemes.

Timing is strict. The building control body or registered third-party certifier must be notified before work starts12. For new buildings, the person carrying out the work must give the local authority notice of the CO2 emission rate calculations and the fabric energy efficiency rate calculations not later than the day before the work starts6, and in any case other than a higher-risk building, notice that the energy analysis has been undertaken and documented must be given not later than the beginning of the day before the day on which the work starts22.

Jobs you need not tell anyone about

A simplified electrician figure fitting a new light switch on an existing circuit in an ordinary room wall of a home, away from any kitchen or bathroom, with the switch faceplate being screwed onto a wall-mounted back box and a short length of cable running into the wall.
Adding a light switch is not notifiable

Not everything needs a building control application. The Building Regulations allow certain works, known as non-notifiable or minor work, to be carried out without having to notify building control or use a registered electrician23. For electrical work in homes and gardens, you do not need to tell the building control body about repairs, replacements and maintenance work, or about extra power points or lighting points or other alterations to existing circuits, except in a kitchen or bathroom, or outdoors23. Most repairs, replacements and maintenance jobs, and alterations or additions to existing circuits outside special locations, fall outside notification12.

Local authority guidance fills in the detail. Work that need not be notified to the council includes adding lighting points, light fittings and switches, to an existing circuit, and installing or upgrading main or supplementary equipotential bonding, where the work is not in a kitchen or special location and does not involve a special installation24. The same authority states the other side of the line: notifiable work must be inspected and tested either by a member of the Competent Person Scheme or through a Building Regulations Application21.

There is also a notification exemption built into the approval system itself. For certain types of services or fittings, including fuel-burning appliances or replacement windows, a building control body does not need to be notified if the owner employs an installer registered with a relevant competent person scheme designated in the regulations6. In other words, the work is still regulated, but the registered installer's self-certification replaces the notification. The distinction matters when something goes wrong: work that was never notifiable has no certificate trail to worry about, whereas work that was notifiable but self-certified should have been certified by the installer.

Buildings and projects outside the rules

Some kinds of building projects are exempt from the regulations17. In Scotland, regulations 8 to 12 do not apply to any building or any services, fittings and equipment the whole of which falls into an exempted type in schedule 1, and any demolition or alteration of the roof, external walls or element of structure is excluded from the house-work exemption14. England's exemptions work on the same principle: whole classes of building or project sit outside the system.

The Energy Performance of Buildings (England and Wales) Regulations 2012 exclude from their Part 2: buildings used as places of worship and for religious activities; temporary buildings with a time of use of two years or less; industrial sites, workshops and non-residential agricultural buildings with low energy demand; and residential buildings used or intended to be used for less than four months of the year25. Regulation 21 of the Building Regulations 2010 similarly excludes buildings listed or in a conservation area or scheduled monuments where compliance would unacceptably alter their character or appearance, places of worship, temporary buildings with a planned time of use of two years or less, industrial sites, workshops, non-residential agricultural buildings with low energy demand, and stand-alone buildings other than dwellings with a total useful floor area of less than 50m222.

For householders, the exemptions that bite are the small ones. A stand-alone building other than a dwelling under 50 square metres is outside the Part L requirement22, and a conservatory under 30 square metres is normally exempt, as section 10 below sets out. But exemption is never a licence to build badly: the exemption for conservatories still requires the glazing and fixed electrical installations to comply with the applicable requirements7.

Part L: saving fuel and power

An interior room of an existing home where a solid external wall is being upgraded with internal insulation, shown as a cutaway with insulation boards being fitted over the masonry and a plain colour band indicating the improved thermal performance.
Insulating a wall cuts energy demand

Part L is the part of the Building Regulations that conserves fuel and power, and it is the part most home energy projects touch. The Approved Document L, Volume 1: Dwellings, in its 2021 edition incorporating 2023 amendments, sets the standards for England6. Its limiting U-values cap how much heat a fabric element may lose. For new fabric elements in existing dwellings, Table 4.2 gives a maximum wall U-value of 0.18 W/(m²·K)6. For new dwellings, the Welsh consultation version of Approved Document L gives a wall value for dwelling houses of 0.18 W/(m²·K)11, while Table 3.1 of the current Approved Document L gives a limiting wall U-value of 0.26 W/(m²·K) for new dwellings6.

These figures are not interchangeable, and it is worth being precise about which is which. The 0.18 W/(m²·K) figure is the standard a new wall is actually expected to achieve, in both England's guidance for existing dwellings and the Welsh consultation for new dwelling houses6. The 0.26 W/(m²·K) figure is a limiting value in Table 3.1: a backstop that no element may exceed even if the dwelling as a whole passes its overall energy performance targets6. A wall built to 0.18 comfortably clears the backstop; a wall built only to the backstop would usually fail the dwelling-level calculation.

Part L also drives the paperwork before work starts. The requirement for CO2 emission rate and fabric energy efficiency rate calculations, notified not later than the day before work starts6, and the notice that the energy analysis has been undertaken and documented22, both sit in this territory. Requirement L3 does not apply to a building which is a relevant building for the purposes of regulation 7(4) of the Building Regulations 20106, which is how listed and protected buildings are handled where compliance would unacceptably alter their character.

The direction of travel is set. The Future Homes and Buildings Standards will be implemented via the Building Regulations etc. (Amendment) (England) Regulations 20269, tightening what new homes must achieve; we cover that separately in the Future Homes Standard.

Who bears responsibility for non compliant work

Responsibility runs on two tracks. On one track, the people responsible for building work, including agents, designers, builders or installers, must ensure that the work complies with all applicable Building Regulations requirements11. If you are employing a builder, the responsibility will usually be theirs, but this should be confirmed at the very beginning of the project17. The Welsh guidance says the same18.

On the other track sits the owner. If you are the owner of the building, it is ultimately you who may be served with an enforcement notice if the work does not comply with the regulations16. The Welsh guidance repeats this18. In Scotland, the duty to comply lies with the owner, or in some cases the client, for the work14. The practical reading is that a builder's responsibility is real but contractual and professional; the owner's exposure is statutory and attaches to the building, surviving the builder's departure from the scene.

There are also specific notice duties on the person carrying out the work. Under regulation 7A, which applies where a building is erected in England and Wales, the person carrying out the building work must give the local authority notice to that effect26. The person doing the work could be prosecuted and fined if they do not comply with building regulations2. For a household, the lesson is to settle who is handling approval in writing before work starts, because an enforcement notice lands on the owner regardless of who cut the corners.

Certificates, enforcement and work done without approval

A completion certificate as a physical paper document lying on a solicitor's desk in an office, held or passed across by a small simplified figure, its content shown only as blank lines and plain blocks so nothing readable appears.
A completion certificate proves the work

The Building Regulations 2010 define unauthorised building work in regulation 18: building work, other than work in relation to which an initial notice, an amendment notice, a public body's notice or a regulator's notice has effect, which is done without a building notice, an application for building control approval with full plans, or a notice of intention to start work in the circumstances specified27. The Wales version of the regulation is materially the same27. In plain terms, work that needed a route into the system and never took one is unauthorised.

The consequences are financial and practical. You may have to correct the work or pay a fine if building regulations are not followed5. If building regulations approval is not given, then the work should be changed so it meets standards20. The person doing the work could be prosecuted and fined2. Beyond the immediate penalty, unauthorised work leaves no certificate, and certificates matter later: nothing in Part 2 of the Energy Performance of Buildings Regulations requires an energy performance certificate to be given or made available to a prospective buyer or tenant before construction of the building has been completed25, which is one example of how completion and certification unlock the paperwork of selling or letting.

The certificate itself is issued at the end. Once the building control body has decided that the work meets all the Building Regulations requirements, it will issue a Building Regulations completion certificate if it is a building control authority, or a final certificate if it is a registered building control approver6. The Welsh guidance describes the same split for heat pump installation work11. Where electrical works are involved, an Electrical Installation Certificate signed by a competent person must be provided, and until that certificate is received a Completion Certificate for the whole of the works cannot be issued21. In Scotland, the equivalent step is the owner or client certifying on completion that the works have been constructed in accordance with the building warrant and the building regulations14.

How extensions, glazing, conservatories and solar affect existing homes

Existing homes meet the regulations differently from new builds, and the common projects each have their own pattern.

Extensions. Building regulations will generally apply if you want to build an extension to your home28. There is no floor-area threshold for an extension in the way there is for a conservatory: the extension is building work under regulation 3 from the outset16.

Conservatories. Conservatories are normally exempt from building regulations when they are built at ground level, single storey, and less than 30 square metres in floor area; separated from the house by external quality walls, doors or windows; and heated by an independent heating system with separate temperature and on/off controls. The glazing and any fixed electrical installations must comply with the applicable building regulations requirements7. The Welsh guidance states the same conditions28. The trap is the junction: any new structural opening between the conservatory and the existing house will require building regulations approval even if the conservatory itself is an exempt structure7.

Windows and glazing. Replacing windows and doors is work covered by building regulations approval2. Planning permission is a separate question with its own rules: for flats and maisonettes, replacement windows do not require planning permission so long as they are identical like-for-like replacements in appearance and material, but permission is likely if the new windows would not match the existing appearance, material or glazing type, including a change between single and double or triple glazing; and for a listed dwelling house, planning permission would be required for replacement windows29.

Roofs. Work to the roof of a house, such as re-roofing, that does not materially affect its external appearance will usually not require planning permission30. That is a planning statement, not a building regulations one: structural work to a roof is an alteration and falls to be assessed under regulation 3.

Solar panels. Installing solar panels may require approval under the Building Regulations, because of the associated electrical works32. Building regulations will normally apply to installing solar panels on your roof33, and a building regulations application is needed when installing a solar panel on a roof, with the roof strength assessed and possibly strengthened34. Planning is again separate: placing solar panels on the roof of a house or flat, or on a building within its grounds, is considered in most cases permitted development under the 2015 Order, Schedule 2, Part 14, Class J33, and installation on residential buildings may be permitted development with no need to apply for planning permission35. But solar panels on listed buildings need planning permission and listed building consent34, and listed building consent is needed before work can commence32. We cover the planning side in permitted development rights and listed buildings.

The impact on a household's independence

A registered installer in plain work clothing kneels beside a newly installed wall-mounted electrical unit in a home, completing a certificate on a clipboard with a pen, the self-certification record for notifiable electrical work shown as blank lines only.
A registered installer self certifies the work

The building regulations are one of the few levers the state holds over how far a home can go energy-independent, and they cut both ways. On the one hand, they are a condition on almost every step towards self-sufficiency: solar panels on a roof, a new heating appliance, cavity wall insulation, replacement glazing and hot water cylinders are all building work or controlled fittings16, and each needs either a building control application or a registered installer's self-certification5. A household cannot quietly re-engineer its own home outside the system.

On the other hand, the system is designed to be passable. The competent person route means a registered installer of windows, boilers or electrical work self-certifies, and no separate approval is needed5. Minor work, including most repairs and additions to existing circuits outside kitchens, bathrooms and outdoors, needs no notification at all23. The exemptions cover genuinely small structures, from conservatories under 30 square metres to stand-alone buildings under 50 square metres28.

The dependence that remains is on the inspection and certification chain: a building control body or a scheme-registered installer, and ultimately the local authority that can serve an enforcement notice on the owner16. The certificate at the end is the household's proof of compliance, needed for the sale or letting of the property and unobtainable while an Electrical Installation Certificate is outstanding21. The rules also move: the 2021 amendments changed the guidance8, the 2026 regulations will implement the Future Homes and Buildings Standards9, and a project is judged by the rules in force when it is approved. A household planning energy work does well to check the current position before starting, not after.

Sources35 sources
  1. Planning permission and building regulations: the difference, Planning Portal
  2. Building regulations approval, GOV.UK
  3. The difference between building regulations and planning permission, Planning Portal
  4. Approved Document L, Conservation of fuel and power, Volume 1: Dwellings, 2021 edition incorporating 2023 amendments, GOV.UK
  5. Use a competent person scheme, GOV.UK
  6. Approved Document L, Volume 1: Dwellings, GOV.UK
  7. Conservatories: building regulations, Planning Portal
  8. Part F Ventilation: previous editions, Planning Portal
  9. RPC opinion: Future Homes and Buildings Standards impact assessments, GOV.UK, 2026-03-25
  10. The Building Regulations etc. (Amendment) (England) (No. 2) Regulations 2021, legislation.gov.uk, 2021-12-13
  11. Approved Document L Volume 1, consultation version, Welsh Government, 2025-08
  12. Building regulations for electrics: general information, Planning Portal
  13. Building regulations approval: how to apply, GOV.UK, 2026-09-17
  14. Building Standards Technical Handbook, Domestic, April 2026, Scottish Government, 2026-03
  15. Building regulations in Northern Ireland, buildingcontrol-ni.com
  16. Building regulations: when you need approval, Planning Portal
  17. Building regulations, Planning Portal
  18. Building regulations in Wales: when you need approval, Planning Portal
  19. Building regulations guidance, Part J: heat producing appliances, archived, Welsh Government, 2025-01
  20. Electric vehicle charging: building regulations, Planning Portal
  21. Building regulations and electrical works, London Borough of Richmond upon Thames, 2026-06-02
  22. The Building Regulations 2010, Part 6, legislation.gov.uk
  23. Building regulations: electrics in Wales, Welsh Government
  24. Electrical safety: building regulations in Carlisle, Cumberland Council
  25. The Energy Performance of Buildings (England and Wales) Regulations 2012, Regulation 5, legislation.gov.uk
  26. The Energy Performance of Buildings (England and Wales) Regulations 2012, Regulation 7A, legislation.gov.uk
  27. The Building Regulations 2010, Regulation 18, legislation.gov.uk
  28. Building regulations: conservatories in Wales, Welsh Government
  29. Planning frequently asked questions: replacement windows, London Borough of Hammersmith and Fulham
  30. Roof planning permission, Planning Portal
  31. Roof projects, Planning Portal
  32. Solar panels guidance, City of York Council
  33. Solar panels and planning permission, Wirral Council
  34. Solar panels and planning permission, Cornwall Council
  35. Solar photovoltaic (PV) panels, London Borough of Bromley

Questions

Some answers here, the rest on their own pages.

Do I need building regulations approval to install solar panels?

Yes, in most cases. Installing solar panels on your roof normally requires a building regulations application, both because the roof must be assessed for strength and possibly strengthened, and because of the associated electrical works. Planning permission is a separate matter: roof-mounted panels on a house are usually permitted development, but panels on a listed building need planning permission and listed building consent before work starts.

How do I get a completion certificate for building work?

Once the building control body that oversaw your work is satisfied it meets all the requirements of the Building Regulations, it issues the certificate. A local authority issues a Building Regulations completion certificate; a private registered building control approver issues a final certificate. If the work included electrical installation, an Electrical Installation Certificate signed by a competent person must be provided before the completion certificate for the whole works can be issued.

Do replacement windows have to meet building regulations?

Yes. Replacing windows and doors is covered by building regulations approval. In practice, most installers are registered with a competent person scheme and self-certify the work, which is instead of getting separate approval. Planning permission is a different question: for flats and maisonettes, like-for-like replacements do not need it, but permission is likely if the new windows would not match the existing appearance, material or glazing type.

Is a conservatory exempt from building regulations?

Normally yes, if it meets all the conditions: built at ground level, single storey, under 30 square metres in floor area, separated from the house by external quality walls, doors or windows, and with its own independent heating with separate temperature and on/off controls. The glazing and any fixed electrical installations must still comply. Any new structural opening between the conservatory and the house needs approval even if the conservatory itself is exempt.

Do I need to notify the Health and Safety Executive before starting work?

Possibly, and it is separate from building regulations. If you are carrying out, or having construction or building work done, you may need to notify the Health and Safety Executive and may have other duties as well. Separately, the building control body or registered third-party certifier must be notified before the work starts, and in almost all cases of new building work a building control body must be notified in advance of any work starting.

Who checks electrical work in a dwelling?

Safety can be checked in one of two ways: either an electrician registered with a competent person scheme does the work and self-certifies that it complies, or the work is notified to the building control section of the local authority, which inspects and tests it. The Building Regulations set standards for electrical installation work only in relation to dwellings; in industrial or commercial buildings the Health and Safety Executive is responsible.

Can I be fined for building work without approval?

Yes. The person doing the work could be prosecuted and fined if they do not comply with building regulations, and you may have to correct the work or pay a fine if the regulations are not followed. Work done without the required notice or application is unauthorised building work, and if approval is not given, the work should be changed so it meets standards. As the owner, you may be served with an enforcement notice.